IDCS was selected to participate as a sub-consultant to Greeley & Hansen for the project to add ultraviolet disinfection facilities to the Terrence J. O’Brien (North Side) Water Reclamation Plant.
MWRDGC initiated a project for the replacement of a portion of the 1920’s Westside Treatment Plant at the Stickney WRP with new Aerated Grit Facilities and Primary Settling Tanks.
IDCS worked as a sub-consultant to SpecPro for power studies for an Air Force base located in Minot North Dakota. Utilizing SKM software IDCS completed a short circuit study which included over 300 bus points from the incoming service entrance to the panelboard distribution level.
Tyndall AFB Medical Center is a 50,000 square foot building contained over 70 distribution panels in various stages of life, as well as 30 transformers. The scope of this project was to update and eliminate panels and transformers where possible and create a new efficient electrical distribution system.
IDCS was a sub-consultant on the City of Evanston Water Utility electrical hazard assessment. The project included the assessment of the entire water treatment facility, and furnishing the required field markings (labels) for the electrical distribution equipment.